Boiler Plant Demolition Update
Sunday, 7-15-01

Last Update

More updates:   7-16       7-17       7-20       7-30       8-09
The photo below shows the current state of the boiler plant demolition. The north and south wings have been demolished. Click on the photo for a high-resolution view zoomed in on the building.  You'll notice a wheel-like object in the basement at the corner of the building nearest you.  This is the generator, the only part of the plant that will be kept. The generator was prepared for removal Saturday and is scheduled to be removed Monday starting about 11:30 AM.
We've been videotaping the demolition since it began on June 28. We're using a time lapse method so that we can get the entire process on one or two tapes. For a video preview of one day of the demolition, click on the link below. We also provide links to photo updates and a live video feed.